Annual Pavement Management
Project #619
View on Interactive Map →The Town is responsible for maintaining 240 miles of municipal streets with an annual resurfacing contract providing for most pavement maintenance needs. Street mileage is growing annually with ongoing development. A recent survey of our streets revealed that deferred maintenance needs to be addressed. This ongoing program focuses on deficiencies in pavement conditions throughout Apex and addresses issues, such as potholes, alligator cracking, and rutting, to provide a safe and reliable transportation system. This program also includes lower cost pavement preservation tools to extend pavement life cycle and reduce long term resurfacing costs while ensuring curb ramps on all resurfacing projects comply with state and federal mandates. Powell Bill funding is allocated from the State for road maintenance, but current and future resurfacing costs continue to exceed Powell Bill allocations, requiring General Fund revenues to be allocated.
Project Details
- Status
- Ongoing
- Priority
- Medium
- Funding Source
- Intergovernmental Funds (Powell Bill Revenues), Designated Capital Funds
- Start Date
- July 2024
- Construction Start
- *
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $3,750,000 |
| FY 2027 | $3,875,000 |
| FY 2028 | $4,000,000 |
| FY 2029 | $4,125,000 |
| FY 2030 | $4,250,000 |
| Future | $4,375,000 |
| Total Cost | $24,375,000 |