Transportation

Olive Chapel Road at Apex Barbecue Road Improvements

Project #622

View on Interactive Map →

This project addresses traffic congestion and reduces potential crashes at the intersection of Olive Chapel Road and Apex Barbecue Road by adding a 150-foot westbound left turn lane, 6-foot paved shoulders allowing for future bike lanes, rumble strips along the edge lines, a wider eastbound right-turn radius, and a wood-pole traffic signal on Olive Chapel Road at Apex Barbecue Road. This project completes a sidewalk gap with 500’ of 10-foot side path eastward along the north side of Olive Chapel Road.

Project Details

Status
Planning
Priority
Medium
Funding Source
Designated Capital Funds, Grants, General Fund / Capital Outlay
Coordinates
35.72986154, -78.90612602
Start Date
July 2024
Estimated Completion
June 2027

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$600,000
FY 2028$0
FY 2029$0
FY 2030$0
Future$0
Total Cost$600,000

Location

Open in cipmap →