This project upgrades an existing section of Jessie Drive from west of Ten Ten Road to the Horton Park development boundary using half of a 4-lane divided roadway with 10' side path on both sides and increasing to the ultimate 4-lane width in advance of Ten Ten Road. The Horton Park development will extend Jessie Drive west to the future Production Drive and a collector street south to Colby Chase Drive. The Apex Commerce Center project will extend Production Drive south to Jessie Drive, providing local connectivity north and south.

Project Details

Status
Design
Priority
Medium
Funding Source
General Obligation Bonds
Coordinates
35.70756223, -78.81437302
Start Date
July 2025
Estimated Completion
June 2026

Funding Schedule

Fiscal YearAmount
FY 2026$8,500,000
FY 2027$0
FY 2028$0
FY 2029$0
FY 2030$0
Future$0
Total Cost$8,500,000