Transportation

Chatham Street Sidewalk Phase 2

Project #636

View on Interactive Map →

This project completes additional sidewalk gaps across the Center Street and Chatham Street railroad crossings where prior projects upgraded the crossings and completed the sidewalk gaps on one side of each road. This project completes sidewalk gap along the south side of E. Chatham Street between N. Mason Street and the existing sidewalk fronting Clairmont Park.

Project Details

Status
Not Started
Priority
Medium
Funding Source
General Fund / Capital Outlay, TBD
Coordinates
35.73176888, -78.84816885
Start Date
July 2026
Estimated Completion
June 2029

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$230,000
FY 2028$260,000
FY 2029$1,440,000
FY 2030$0
Future$0
Total Cost$1,930,000

Location

Open in cipmap →