Chatham Street Sidewalk Phase 2
Project #636
View on Interactive Map →This project completes additional sidewalk gaps across the Center Street and Chatham Street railroad crossings where prior projects upgraded the crossings and completed the sidewalk gaps on one side of each road. This project completes sidewalk gap along the south side of E. Chatham Street between N. Mason Street and the existing sidewalk fronting Clairmont Park.
Project Details
- Status
- Not Started
- Priority
- Medium
- Funding Source
- General Fund / Capital Outlay, TBD
- Coordinates
- 35.73176888, -78.84816885
- Start Date
- July 2026
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $230,000 |
| FY 2028 | $260,000 |
| FY 2029 | $1,440,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $1,930,000 |