Chatham Street Sidewalk Phase 2
Project #636
View on Interactive Map →This project completes additional sidewalk gaps across the Center Street and Chatham Street railroad crossings where prior projects upgraded the crossings and completed the sidewalk gaps on one side of each road. This project includes sidewalk along the north side of Center Street from N. Salem Street to N. Mason Street and sidewalk along the south side of Chatham Street from S. Salem Street to S. Elm Street and from N. Mason Street to the cul-de-sac and existing sidewalk in front of Clairmont Park. The project serves Safe Routes to School needs for Apex Middle School.
Project Details
- Status
- Not Started
- Priority
- Medium
- Funding Source
- General Fund / Capital Outlay, TBD
- Coordinates
- 35.73176888, -78.84816885
- Start Date
- July 2026
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $230,000 |
| FY 2028 | $260,000 |
| FY 2029 | $1,440,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $1,930,000 |