This project replaces the Hunter Street Park turf field, which was installed in 2016. This field has experienced heavy usage and is beginning to show signs of wear. A new all-weather field is expected to last about ten years. This renovation increases paved surfaces and adds accessible visitor areas. This project also installs a retaining wall and slope stabilization to reduce erosion on the field surface and address stormwater concerns.

Project Details

Status
Not Started
Priority
Medium
Funding Source
General Fund / Capital Outlay
Coordinates
35.73737744, -78.84801865
Start Date
July 2025
Estimated Completion
June 2027

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$1,000,000
FY 2028$0
FY 2029$0
FY 2030$0
Future$0
Total Cost$1,000,000