Fire Station 3 Renovation/Addition
Project #676
View on Interactive Map →This project renovates and expands Fire Station 3 to accommodate the engine company of crew from Fire Station 1 when Fire Station 1 closes. This project addresses insufficient kitchen, living room, bedroom, locker, and bathroom space in addition to age-related renovations (flooring, paint, fixtures, plumbing, etc.).
Project Details
- Status
- Design
- Priority
- Medium
- Department
- Fire
- Funding Source
- Installment Purchase / Capital Lease
- Coordinates
- 35.73579245, -78.86082888
- Start Date
- July 2024
- Construction Start
- December 2026
- Estimated Completion
- May 2028
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $8,100,000 |
| FY 2027 | $0 |
| FY 2028 | $0 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $0 |