Parking Lot and Internal Street Assessment & Long Maintenance Plan
Project #680
View on Interactive Map →This project maintains and repairs the Town’s parking lots and internal streets. The schedule is informed by the Parking Lot and Internal Street Assessment and Long Maintenance Plan. First-year funds replacement and repair of Public Safety Station 4's rear parking lot and rear drive due to near complete failure in spots and expanding depressions.
Project Details
- Status
- Ongoing
- Priority
- Medium
- Funding Source
- General Fund / Capital Outlay
- Start Date
- July 2025
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $350,000 |
| FY 2028 | $0 |
| FY 2029 | $115,000 |
| FY 2030 | $110,000 |
| Future | $1,100,000 |
| Total Cost | $1,675,000 |