Town Wide Solar Initiative
Project #681
View on Interactive Map →This project designs and constructs solar panels on twelve Town facilities over a two-year period. Solar projects are selected and prioritized based on the Town’s Solar Panel Assessment.
Project Details
- Status
- Construction
- Priority
- Medium
- Funding Source
- General Fund / Capital Outlay
- Start Date
- July 2025
- Estimated Completion
- June 2027
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $100,000 |
| FY 2028 | $570,000 |
| FY 2029 | $670,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $1,340,000 |