Fleet Fluid Pumps/Reclamation
Project #684
View on Interactive Map →This project relocates reservoirs for motor oil, hydraulic, coolant, and reclamation. Compared to current conditions, the reservoirs will be relocated to a larger area with larger fluid and reclamation tanks that use pneumatic pumps to more safely and efficiently remove used fluids. This project reduces the risk of spills, overflows, and hazards while also making liquid refills and removal less frequent.
Project Details
- Status
- Not Started
- Priority
- Medium
- Department
- Fire
- Funding Source
- General Fund / Capital Outlay
- Start Date
- July 2028
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $0 |
| FY 2028 | $0 |
| FY 2029 | $115,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $115,000 |