Right of Way Mowing Tractor - Replacement
Project #694
View on Interactive Map →This project replaces a right of way mower (Unit #556) that will be 24 years old with over 1,600 hours of use at the replacement time.
Project Details
- Status
- Not Started
- Priority
- Medium
- Funding Source
- Installment Purchase / Capital Lease
- Start Date
- July 2026
- Estimated Completion
- June 2027
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $0 |
| FY 2028 | $0 |
| FY 2029 | $170,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $170,000 |