This project funds the engineering and construction costs needed to add electrical capacity (via a 40-megavolt-ampere power transformer) to the existing East Williams Substation. This additional capacity will improve the Town’s ability to serve the Veridea development and other residents in the surrounding area.

Project Details

Status
Planning
Priority
Medium
Coordinates
35.71220553, -78.83952677
Start Date
July 2024
Estimated Completion
June 2027

Funding Schedule

Fiscal YearAmount
FY 2026$1,925,000
FY 2027$1,650,000
FY 2028$0
FY 2029$0
FY 2030$0
Future$0
Total Cost$3,575,000