This project designs and constructs the Green Level Substation in the northwest corner of Apex. This substation will serve a growing population and alleviate demand from the Laura Duncan and Mount Zion substations. This substation will provide an imperative system redundancy and increase reliability by reducing feeder exposure.

Project Details

Status
Planning
Priority
Medium
Coordinates
35.74770084, -78.91419947
Start Date
July 2024
Estimated Completion
June 2028

Funding Schedule

Fiscal YearAmount
FY 2026$500,000
FY 2027$1,750,000
FY 2028$2,350,000
FY 2029$0
FY 2030$0
Future$0
Total Cost$4,600,000