Green Level Substation
Project #699
View on Interactive Map →This project designs and constructs the Green Level Substation in the northwest corner of Apex. This substation will serve a growing population and alleviate demand from the Laura Duncan and Mount Zion substations. This substation will provide an imperative system redundancy and increase reliability by reducing feeder exposure.
Project Details
- Status
- Planning
- Priority
- Medium
- Coordinates
- 35.74770084, -78.91419947
- Start Date
- July 2024
- Estimated Completion
- June 2028
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $500,000 |
| FY 2027 | $1,750,000 |
| FY 2028 | $2,350,000 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $4,600,000 |