Electric Utility

Veridea System Expansion

Project #706

View on Interactive Map →

This project expands the Town’s electric system to support the Veridea development, a proposed sustainable, mixed-use urban community on 1,100 acres within the Town of Apex. Expanding the existing electric infrastructure is needed to serve a development of this size.

Project Details

Status
Planning
Priority
Medium
Coordinates
35.69801344, -78.84990692
Start Date
July 2025
Estimated Completion
June 2029

Funding Schedule

Fiscal YearAmount
FY 2026$2,500,000
FY 2027$3,000,000
FY 2028$3,000,000
FY 2029$2,500,000
FY 2030$1,300,000
Future$0
Total Cost$12,300,000

Location