HL-0007: NC 55 Intersection Improvements Utility Relocation
Project #716
View on Interactive Map →This project relocates water and sewer utilities, including water lines, fire hydrants, valve, sewer lines, and manholes, to accommodate NCDOT’s widening of NC 55. Utilities in conflict must be relocated to prevent disrupting customer utility service within the construction corridor.
Project Details
- Status
- Planning
- Priority
- Medium
- Coordinates
- 35.69484187, -78.83525133
- Start Date
- July 2025
- Estimated Completion
- June 2027
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $500,000 |
| FY 2027 | $1,235,000 |
| FY 2028 | $0 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $1,735,000 |