Waterline Gaps (Humie Olive)
Project #722
View on Interactive Map →This project provides waterline connections in the Humie Olive area at the following locations: 1) along at least two segments of Humie Olive Road to complete a loop in this area and provide necessary redundancy to the New Hill/Jordan Pointe service area, 2) along Humie Olive to the nearest Friendship Station blowoff on Olive Farm Road, 3) between two existing blowoffs along Richardson Road, and 4) along Mount Zion Church Road to connect to the existing water line along 47 Flourine Drive.
Project Details
- Status
- Not Started
- Priority
- Medium
- Coordinates
- 35.70433877, -78.91970873
- Start Date
- July 2026
- Estimated Completion
- June 2028
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $105,000 |
| FY 2028 | $410,000 |
| FY 2029 | $460,000 |
| FY 2030 | $0 |
| Future | $475,000 |
| Total Cost | $1,450,000 |