Waterline Gaps (US 64/Salem)
Project #723
View on Interactive Map →This project completes several water line connections along the US 64 corridor near N. Salem Street, eliminating several existing water line gaps from development. These segments include the following locations: 1) between All Wheel Drive and Taywood Way, 2) between Horsham Way and Carolina Bell Road, 3) along US 64 to connect the Villages at Apex to N. Salem Street, 4) crossing Apex Peakway to connect the Villages of Apex South to the Villages of Apex, 5) from the existing blowoff on Davis Drive to N. Salem Street near Crossroads Ford crossing US 64, 6) from the Davis Drive and N. Salem Street intersection to a water line near 1701 N. Salem Street, and 7) between Castlewood and the Orchard Villa subdivisions by crossing US 64.
Project Details
- Status
- Not Started
- Priority
- Medium
- Coordinates
- 35.74954246, -78.85136604
- Start Date
- July 2026
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $200,000 |
| FY 2028 | $900,000 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $2,930,000 |
| Total Cost | $4,030,000 |