Stormwater Utility

Lake Pine Dam Rehabilitation/Replacement

Project #737

View on Interactive Map →

This project conducts a spillway study at the Lake Pine dam, located at the Apex Community Park, which is classified by the State to be a high hazard dam. This study would potential solutions and alternatives for rehabbing or replacing the Lake Pine spillway in order to increase climate resiliency, water quality, and flood control capability of Lake Pine. Not pursuing a spillway study would result in further deterioration of the current spillway and potentially endanger properties downstream.

Project Details

Status
Not Started
Priority
Medium
Coordinates
35.74728723, -78.81669044
Start Date
July 2025
Estimated Completion
June 2027

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$0
FY 2028$0
FY 2029$0
FY 2030$0
Future$22,000,000
Total Cost$22,000,000

Location

Open in cipmap →