View on Interactive Map →This project adds a new aerial ladder fire truck to support the need for a second fire crew (ladder) at the Olive Chapel Road fire station. The addition of this apparatus will ensure that this station has the necessary equipment to meet the needs of a growing community and department.
Project Details
- Status
- Not Started
- Priority
- Medium
- Start Date
- July 2029
- Estimated Completion
- June 2030
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $0 |
| FY 2027 | $0 |
| FY 2028 | $0 |
| FY 2029 | $0 |
| FY 2030 | $2,837,500 |
| Future | $0 |