Hughes Street Mixed-Use Development
Project #753
View on Interactive Map →To prepare for housing and commercial development on this Town-owned site, street, water, and sewer infrastructure will be designed and built first. The project includes widening ~750 feet of Perry Rd to 35-foot width which includes shared lane markings and a five-foot concrete sidewalk, widening ~750 feet of South Hughes Street to 35-foot width which includes a 10-foot asphalt side path, and constructing ~3,000 feet of new on-site residential streets at 27-foot width with five-foot sidewalks on both sides.
Project Details
- Status
- Not Started
- Priority
- Medium
- Coordinates
- 35.718172603179944, -78.85011076927186
- Start Date
- July 2025
- Estimated Completion
- June 2027
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $2,050,000 |
| FY 2027 | $8,625,000 |
| FY 2028 | $0 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $10,675,000 |