Project Details

Status
Not Started
Priority
Medium
Start Date
July 2029
Estimated Completion
June 2030

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$0
FY 2028$0
FY 2029$0
FY 2030$575,000
Future$0
Total Cost$575,000