Water & Sewer Utility

Waterline Gap Green Level Church

Project #779

View on Interactive Map →

This project will add 1,925 linear feet of ductile iron pipe running North from the Ellsworth development, near the Green Level Highschool, parallel to Green Level Church Road and tying into the water line from the Freedom Square development at Green Level West Road. This project will improve water quality in this area by improving redundancy in the system and maintain adequate pressure along these intersections.

Project Details

Status
Not Started
Priority
Medium
Coordinates
35.77602563715311, -78.90267133712769
Start Date
July 2029
Estimated Completion
June 2030

Funding Schedule

Fiscal YearAmount
FY 2026$0
FY 2027$0
FY 2028$0
FY 2029$0
FY 2030$85,000
Future$720,000
Total Cost$805,000

Location

Open in cipmap →