Capitata Crossing Stream Stabilization
Project #781
View on Interactive Map →This project includes repairing the sanitary sewer at Capitata Crossing and restoring the stream away from the direct line of town owned infrastructure. The stream has significantly migrated, exposing sanitary sewer and is expected to expose more over time. The infrastructure will continue to be in danger if the stream restoration does not happen, increasing the risk of a sanitary sewer overflow.
Project Details
- Status
- Not Started
- Priority
- Medium
- Department
- Water & Sewer Utility; Stormwater Utility
- Funding Source
- Water Resources / Stormwater Utility (cross-listed; counted once)
- Coordinates
- 35.73393745527016, -78.87422919273378
- Start Date
- July 2025
- Estimated Completion
- June 2027
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $175,000 |
| FY 2027 | $450,000 |
| FY 2028 | $0 |
| FY 2029 | $0 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $625,000 |