Culvert Street Drainage and Watershed Repairs
Project #782
View on Interactive Map →This project will remove several large diameter trees, fences, and an older stormwater drop inlet and replace with new stormwater open throat inlet, new stormwater piping, and obtain new public drainage easements that are currently causing significant flooding and drainage concerns in the Downtown area. This project will also explore the entire downtown watershed to assess and recommend a more global approach to improving drainage in the downtown residential area.
Project Details
- Status
- Not Started
- Priority
- Medium
- Coordinates
- 35.730880537198495, -78.84903252124788
- Start Date
- July 2025
- Estimated Completion
- June 2029
Funding Schedule
| Fiscal Year | Amount |
|---|---|
| FY 2026 | $150,000 |
| FY 2027 | $50,000 |
| FY 2028 | $0 |
| FY 2029 | $550,000 |
| FY 2030 | $0 |
| Future | $0 |
| Total Cost | $750,000 |